ABB Commissions, Hands Over DolWin1 Offshore Wind Grid Connection to TenneT

ABB, the leading power and automation technology group, has successfully commissioned and handed over the DolWin1 offshore wind grid connection to the Dutch-German transmission system operator TenneT.

Platform

The 800 megawatts (MW) High Voltage Direct Current (HVDC) link connects offshore wind farms around 75 kilometers off the German coast in the DolWin cluster, with the country’s transmission grid. The DolWin1 grid connection can integrate 800 MW of offshore wind power, enough to supply around one million households with clean energy.

The DolWin1 grid connection is part of Germany’s ambitious energy transition roadmap, called “Energiewende”, which foresees the generation of more than 6.5 gigawatts (GW) from offshore wind by 2020 and 15 GW by 2030.

ABB deployed its Voltage Source Converter (VSC) technology, called HVDC Light®, for the project and was responsible for the design, engineering supply and installation of the offshore and onshore converter stations, as well as the submarine and underground cable systems.

“We are proud to hand over the DolWin1 offshore wind grid connection to TenneT and to make a significant contribution to Germany’s target of increasing its share of renewables in the energy mix,” said Claudio Facchin, President, ABB Power Systems division. “We pioneered HVDC technology and have remained at the forefront of its innovation. We are pleased to see it being leveraged to bring clean energy to millions of people reliably and efficiently.”

The wind farm Borkum West II and the wind farm Borkum Riffgrund I are connected via submarine cables to DolWin alpha, the offshore converter station. Here the alternating current from the wind farms is converted into direct current before being transmitted at a voltage of +/- 320 kilovolts (kV) via 165 kilometers of extruded DC submarine and underground cables to the grid connection point at the Dörpen West substation in Heede, northern Germany.

HVDC is the technology of choice for transmitting large amounts of power, over long distances, efficiently and reliably through overhead, underground and sub-sea links with minimum losses. It is ideally suited for the integration of remotely located renewable energy sources like offshore wind, desert solar or mountain-based hydropower. It is also being increasingly deployed to create cross border interconnections – to strengthen grids and improve the reliability of power supplies. This is a key focus area in ABB’s Next Level strategy.

ABB has been awarded about 100 HVDC projects since it pioneered the technology more than 60 years ago. This represents a total installed capacity of more than 120,000 MW and accounts for around half the global installed base. ABB further developed HVDC in the 1990s by introducing voltage sourced converter (VSC) HVDC technology. ABB leads the way in this technology and, with the DolWin1 project ABB has delivered 16 out of 22 VSC HVDC projects that are in commercial operation around the world.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.